$43 million project to renovate Rouss Hall and construct an 115,000 square foot addition for the Commerce School.
Project Start: January 2005
What's Done: Work on Varsity Hall and Hospital Drive to accommodate Varsity Hall's relocation opposite East Range.
In Progress: Shoring up of Varsity Hall structure for move.
What's Next: Relocation of Varsity Hall in April, interior demolition and asbestos removal in Rouss Hall.
Estimated Completion Date: July 2007