Rouss Hall

$43 million project to renovate Rouss Hall and construct an 115,000 square foot addition for the Commerce School.

Project Start: January 2005

What's Done: Work on Varsity Hall and Hospital Drive to accommodate Varsity Hall's relocation opposite East Range.

In Progress: Shoring up of Varsity Hall structure for move.

What's Next: Relocation of Varsity Hall in April, interior demolition and asbestos removal in Rouss Hall.

Estimated Completion Date: July 2007

Local Savings

Puzzles
Hoos Spelling

Latest Podcast

In this episode of On Record, Allison McVey, University Judiciary Committee Chair and fourth-year College student, discusses the Committee’s 70th anniversary, an unusually heavy caseload this past Fall semester and the responsibilities that come with student-led adjudication. From navigating serious health and safety cases to training new members and launching a new endowment, McVey explains how the UJC continues to adapt while remaining grounded in the University's core values of respect, safety and freedom.